.Sept. 28 – Gathering and building my assets. Animatic due today.
Sept. 30 – Still building assets and getting ready to finalize the format that this will be presented in.
October 5 – Sit down with Jill for a small one on one crit of any effects/transitions that I am questioning.
October 7 – work/animate
October 11 – 15 – Mid-Term Grading – work/animate/small crit in front of the class from there of where I am at.
( October 12 ) – KEEP PUSHING THROUGH THE ANIMATING PROCESS (OPTIONAL DAY FOR DOING THE NEW SETTINGS IN AFTER EFFECTS, ROTOSCOPING AND SUCH!)
(October 14 ) – ANIMATING
October 18 – 19 – Fall Break – I should at least have the first act nearing completion with the second act started on.
October 21 – Gathering more material and research if needed, animating/looking for crit of progress
October 26 – Animating
October 28 – Crit on work
November 2 – Animate
November 4 – Animate
November 9 – A work crit/then back to animating
November 11 – Doing some revisions and touch ups to make everything look nice and clean
November 16 – Draw and plan out the DVD portion of how this is going to be presented
November 18 – Do some more touch ups and animating
November 23 – By now I should be done with act 1 and nearing any final renders on act 2 and should be well within completing act 3
November 25 – Thanksgiving - animating
November 30 – Going over everything for the final time and seeing if I am done with act 3.
December 2 – WORKING MY BUTT OFF TO MAKE SURE EVERYTHING IS TOP NOTCH
December 7 – WORKING ON ITTTTTTTT!!!
December 9 – Present my final work and pray that it is awesome
December 17 – Classes End